Village Hall
282 South Broadway
South Nyack, NY 10960
(845) 358-0287

Latest News

Tuesday, May 7, 2013

Tappan Zee Bridge Task Force Report

The Tappan Zee Bridge Task Force and Mayor Christian met today with representatives from the Tappan Zee Bridge project team to discuss construction noise and vibration monitoring.

The project team described their plan to monitor noise, vibration, and air quality during construction; the limits they are not to exceed; and how they will respond if a limit is exceeded. The project website now has a page dedicated to Environmental Monitoring, http://newnybridgegallery.com/noise/. The site describes the monitoring plan and provides real-time display of noise, vibration, and air quality measurements from the monitoring locations.

Construction Hours and Noise Limits

The project contract restricts construction activities late at night (10pm to 6am), Saturday morning until midday and Sunday all day. During that time, no equipment can be used that emits noise above 70 dBA max measured at an offset distance of 50 feet if the work is on land and at the nearest point of the shoreline if the work is in the water.

During non-restricted working hours, noise limits are based on the specific equipment being used. The nosiest activity will be pile driving, with noise levels at 50 feet of upwards of 90dbA. The table of limits is shown on the website. While these limits are allowed by contract until 10pm, TZC says their plans are to start M-F at 6am and end work by 5pm. They say they will work M-F 5pm-10pm and Saturday 12n-10pm only if they get behind schedule.

We reiterated the Village's previously stated position that noisy construction should be limited to M-F 8am to 7pm with no construction activities on weekends or Federal holidays.

Perceived noise, particularly from pile driving, will be the greatest as the construction gets closer to our shoreline. While it is expected that pile driving farther out in the river will not reach 90db at the shoreline, we expressed concern that repetitive pounding, even at lower decibel levels can be very disturbing. They described that piles will be set mostly be vibrating them into the riverbed. This is much quieter than impact hammering. Once the pile is mostly set using the vibratory hammer, it will be impact hammered at the end to set it into place with a few strikes. They said we should expect that to typically be the nosiest activity and would occur towards the end of the shift.

Monitoring Locations

On the Rockland side, the proposed plan is to place monitoring stations at the shoreline just north and south of the bridge. One at Salisbury Point and one at #28 River Rd. They have asked the Village for permission to place a third monitoring station at Village Hall.

We expressed concerns about the monitoring of construction activities on land between the shoreline and Exit 10. This includes the use of Exit 10 as a staging area and the construction of the shared-use (bike/pedestrian) path and the temporary AETC structures. We believe monitors should be installed to make sure the residential neighborhoods on either side of the Thruway do not experience noise levels above the limits. We asked for their acoustic engineers to look how noise will be received in the hillside neighborhoods overlooking the Thruway.

We also requested the contractor look for ways to minimize the perceived noise from backup alarms on our residents. The trestle (pier) is being made narrower than originally designed, so we asked for them to make sure the revised design still allows for trucks to enter and leave without backing up. The same consideration should be used in the Exit 10 staging area.

Vibration

The project team described their vibration monitoring plan. They said the expected levels of generated vibrations to be well below the levels that could cause structural damage. However, they have identified properties in close proximity to the construction zone to offer pre-construction surveys and installation of vibration monitoring devices. They are in the process of contacting these property owners for permission. Other concerned property owners may request to be included.




Thursday, April 18, 2013

Tappan Zee Bridge Task Force Report

The Tappan Zee Bridge Task Force and Mayor Christian met today with representatives from the Tappan Zee Bridge project team to discuss the proposal to place an All Electronic Toll Collection (AETC) facility in South Nyack. At the April 4 meeting, project representatives had said the AETC was proposed to be located permanently in South Nyack. We expressed concerns about the proposal and asked for more information. (See TZB Task Force report - April 4, 2013.)

The project team told us today that after consideration of our objections and review of the proposal and the TZC contract, they were withdrawing the notion of permanently locating the facility in South Nyack, but still wanted to construct it here temporarily during bridge construction. Towards the end of the project, a permanent AETC facility would be built at the current toll plaza in Tarrytown. The temporary structure in South Nyack would then be removed.

The team showed us maps of the proposed location at Exit 10 and visual simulations of what it would look like. The AETC facility is comprised of an overhead metal gantry that spans the roadway. This holds the EZ-Pass sensors. It also holds cameras that would be used to take photos of the license plates of cars that do not have EZ-Pass. Those drivers would be billed for the toll.

There would be two gantries. One would span the eastbound lanes of the Thruway in the middle of the Exit 10 circular ramp system. A second gantry would be placed on the eastbound entry ramp, just before it passes under 9W. There will also be a small building next to the main gantry to house the AETC recording equipment. Next to the building would be backup generators.

We asked why this location had been chosen. The project team told us that TZC had explored other locations on the Tarrytown side, but they concluded on the Exit 10 site, which was put in the contract accepted by the Thruway Authority. Project engineers reviewed other possible sites with us, contending that there were more difficulties locating the facility on the Tarrytown side.

We expressed concern about possible environmental impacts of the AETC on the Village. The Final Environmental Impact Study (FEIS) was based on a project "limit of construction" just east of the South Broadway overpass. Since the temporary AETC is proposed to be beyond the project limit, we believe a supplemental impact study may be required.

We expressed concern that the Thruway Authority could change their mind some time in the future and decide to leave the AETC permanently in South Nyack. A permanent AETC would complicate the Village's consideration of redevelopment of the Exit 10 area. The project team said they would amend the TZC contract to make it clear that the temporary AETC at Exit 10 is required to be removed. We said that we would also need an agreement between to Thruway Authority and the Village.

We discussed the need for economic development. We pointed out that we have been continually trying to work with the State to bring some benefits to the river villages region. This latest proposal adds yet more burden to South Nyack. We reiterated our requests for some substantive progress on a collaborative effort to attain some benefits.

We concluded saying the Village is wary, but open to accepting the AETC temporarily, but only upon our satisfaction that, 1) there is an enforceable agreement to assure us that the AETC will be only temporary, 2) that environmental impacts are studied appropriately, and 3) that the State demonstrates serious progress towards addressing the issues we have repeatedly raised.




April 4, 2013

Tappan Zee Bridge Task Force Report

The Tappan Zee Bridge Task Force and Mayor Christian met today with representatives from the Governor's office and Tappan Zee Constructors (TZC). When we first met with TZC on February 6, we reviewed outstanding issues to be addressed. We agreed that we would have a series of meetings to address individual issues in more depth. It unfortunately took two months for them to schedule the second meeting.

Construction Schedule

TZC presented a rough construction schedule for the next few months. Pre-construction activities have already started. A barge in the river is being used for sample borings in the riverbed. TZC will also soon begin surveying at the Rockland landing by River Road.

In mid May, TZC will begin relocating overhead utilities to underground. This will involve digging in River Road just north of the bridge and burying the utilities. We expressed concern about disruptions to traffic on River Road. TZC said they will be contacting and cooperating with the South Nyack/Grandview Police.

Construction of the "trestle" will begin mid-summer. This is the pier into the river that will be used transfer personnel and materials to barges. TZC said they have modified the design of the trestle to make it reach farther out into the river and thus reduce the amount of needed dredging. The trestle will also be narrower than originally proposed. We raised a concern that the original wider trestle was designed to allow trucks to enter and leave without backing up. This was intended to avoid the use of backup alarms. We asked if the narrower trestle would eliminate this benefit. TZC said they would look into this issue.

Exit 10 Staging

We discussed the use of Exit 10 for staging. The Thruway has been clearing out their trucks and materials to make way for TZC to use the site. TZC plans to install a chain-link fence around the area with plastic baffles (typically used on tennis courts) and decorated with artwork from local schoolchildren.

We reiterated our opposition to the use of this area. Most of the surrounding neighborhood is much higher than the area and looks down upon it. Fencing will be ineffective for screening. We are also concerned about increased noise, such as backup alarms.

We asked for more details about how the staging area will be used and the amount of traffic expected to travel between the site and the trestle.

AET

TZC informed us that they are proposing to permanently locate an All-Electronic Tolling (AET) facility in the vicinity of Exit 10. This would replace the current Tarrytown toll booths with completely cashless toll collections. Overhead gantries would hold detectors for EZ-Pass tags and cameras to take pictures of the license plates of cars without EZ-Pass and bill them.

We have stressed that the current use ofthe Exit 10 area is inconsistent with the residential neighborhood and is an eyesore. We have continuously pressed for reduction or elimination of this use. Adding the AET increases the inappropriate uses of that area. The addition of the AET structures will add an additional unsightly element, particularly for the hillside neighborhood that overlooks the area. It also interferes with the Village's exploration of economic development for the Exit 10 area.

This proposal is outside of the project limits. It was not studied in the EIS, so its impacts on our Village have not been assessed. We stated that any proposal to expand the project must comply with SEQRA and NEPA requirements.

TZC said they had considered several alternatives. We asked to review these alternatives with TZC.

The Thruway continues to proceed with plans for our Village without consideration of the effects on the Village. They continue to impose impacts on us that we must endure without bringing anything beneficial to our community. We have consistently stated that practical, appropriate solutions can only be developed in collaboration with the Village.

Brian Conybeare,the Governor's representative, noted our concerns and said they would consider other alternatives for siting the AET and continue discussions about this with the Village.

Other Outstanding Issues

When we last met in early February,the State and TZC had agreed to meet regularly with us to address our unresolved issues. It took two months to have this next meeting and no progress was made on the outstanding issues. Instead, a new troubling issue was added. We protested that construction activities are already beginning without resolutions to our issues. We pressed the State to come back immediately to discuss solutions to these issues with us.




February 6, 2013

Initial Meeting with Tappan Zee Constructors

The Mayor and Village officials met today with representatives from the Governor's office and Tappan Zee Constructors (TZC), the contractor that will be building the new Tappan Zee Bridge. This initial meeting was to introduce us to the TZC team and set a framework for addressing issues of concern to the Village. The intention is go more in depth with each issue in subsequent meetings.

Issues were reviewed, including construction impacts, permanent impacts, and issues relating to the Village's vision for redevelopment of Exit 10.

Construction Impacts

  • Construction Hours

    The Thruway's contract with TZC allows TZC to operate from 7 AM to 7 PM M-F and 12 noon to 7 PM on Saturdays. TZC stated, though, that their plan is to work from 7 AM to 3:30 PM M-F. There are some exceptions to this, though. Overtime can happen if activities run late, but TZC intends to avoid this cost. When they are constructing the bridge's main span towers, they will likely work up to 7 PM.

    The Village is concerned that the noise limits allowed in the FEIS and contract may be unreasonably high. We are also concerned that repetitive impacts (from pile driving) would be particularly disturbing, even at lower decibel levels.

    TZC said that pile driving will be the noisiest activity. The trial project last summer did not use any noise mitigation techniques. The actual project will use mostly vibration to set the piles. There will be some impact driving, though. TZC will use mitigation techniques, like shrouds to muffle the noise, but we do not know yet how loud this will end up being. Pile driving is expected to occur starting this summer and will end towards the end of 2014. When pile driving occurs, it will tend to last for a few mid-day hours.

  • Property Damage from Vibration

    TZC is in the process of developing a plan to identify properties most likely to be potentially impacted. They will then work with the property owners to document the existing conditions, to be able to compare later to watch for damage. TZC expressed confidence that there won't be any property damage.

  • Construction Traffic and Parking

    TZC has agreed that no construction trucks will traverse Village streets and workers will not be allowed to park on Village streets. Workers will park in off-site locations and be bussed to the work site. TZC says the vast majority of materials will be brought in by barge on the river. Some trucks will access the pier at the shoreline via the existing maintenance access ramps on either side of the Thruway at River Road. TZC will meet with the Village and police to work out details of enforcement and managing the crossing of River Road.

  • Use of Exit 10 for Staging and Parking

    The area within the Exit 10 circle is a mess, with construction trailers, trucks, and materials. The Village has complained to the State about this for years, but we have been ignored. This construction mess is surrounded by residences and is an inappropriate use. The Village wants the use of this area eliminated. Unfortunately TZC has stated that they intend to use the Exit 10 area for parking, construction trailers, and staging of road construction equipment. The Village expressed our adamant opposition to this and will continue to press to find an alternative solution.

    TZC did confirm that their use of Exit 10 is temporary. They will not be building any permanent structures on the site. The current Thruway maintenance building and NYS Police barracks next to the TZB toll plaza in Tarrytown will be rebuilt at that same location.

    We learned that there is a possibility of a proposal to locate a temporary electronic toll structure over the Thruway in South Nyack. This is apparently not strictly part of the TZB replacement project, but has more to do with the Thruway's recent proposals to explore the use of all-electronic toll collection. We have requested additional details about this proposal and its impacts on the Village.

  • Compliance Enforcement

    TZC and the Thruway will be monitoring impacts, such as noise, and say they have a plan to address violations. The FEIS requires that the Village be involved with development of the plan, but so far the Thruway hasn't included us. The Village has insisted that the compliance plan include not just processes to correct violations, but methods to discourage violations from occurring in the first place.

    Permanent Impacts

  • Noise Barriers

    TZC's plan includes the installation of permanent noise barriers. The exact location and materials are yet to be determined. Local residents, such as Salisbury Cooperative, are continuing to discuss the details with TZC. The Village needs to be actively involved in these discussions to support the residents and ensure that the solution is best for the Village.

  • Shared-use Path Terminus

    The current plan shows the shared-use (bike/pedestrian) path ending at the dead-end of Smith Avenue. The Village was not consulted in this. While the path is purported to be one of the great benefits of the new bridge, the Village has consistently maintained that the Thruway has ignored the potential downsides to the path. Who will use the path? How many people, bicycles? Where will they come from? Where will they park? Will they need bathroom facilities? How will security be maintained? These are permanent local impacts and require local involvement in the planning. The Thruway and TZC have agreed to start planning sessions with us to work collaboratively on the final design.

    Vision for Exit 10

    We also introduced the TZC team to our plan for economic redevelopment of the Exit 10 area. We explained how our vision is to bring permanent jobs, reduce taxes, and contribute to economic vitality for the river villages region. We stressed that details of the bridge landing design, such as the shared-use path, is best done in the context of how it would connect with our future plans. Our plan is designed to leverage the new construction and make it work to the benefit of our community. Just as the Governor has appointed a task force to study mass transit options while the bridge is being built, we have asked that our plans be studied in parallel as well. We were pleased to hear that the State is working on funding for our study.

    Conclusion

    Overall it was a positive meeting. Based on the conversation, we are cautiously optimistic that TZC and the State will make accommodations for most of our concerns. But the proof will be in how they actually deliver on their assurances.

    It was mutually agreed that additional meetings will be held with the Village in the coming weeks to focus on these issues individually.




    February 12, 2013

    The Village of South Nyack has formed a task force to be a single point of contact for communication between the Village of South Nyack and the parties involved in the Tappan Zee Bridge replacement project.

    The three-member task force will, "monitor, communicate, negotiate, and mitigate the effects of the Tappan Zee Bridge project as it relates to the health, safety, and well-being of the citizens of the Village South Nyack," according to the Village. Its duties include:

  • Represent the interests of South Nyack Village government, public safety officers, and property owners during the project.
  • Attend meetings with New York State and the New York State Thruway Authority, State project representatives, project contractor representatives, and elected representatives.
  • Communicate with the public and the press under the direction of the Board of Trustees.
  • Monitor, document, and report to the Board of Trustees construction impacts and compliance with required mitigations.

    The task force members are:

  • Connie Coker, former Rockland County Legislator
  • Jerry Ilowite, Chairman of the South Nyack Planning Board
  • Richard Kohlhausen, South Nyack representative to the TZB design selection committee.


    December 5, 2012

    Advisory Committee Makes Design Recommendation

    A New York State advisory committee has made a recommendation to the Thruway Authority from among the three proposals under final consideration. The three finalists are Fluor Corp., Bechtel Group, Inc., and Skanska AB. The governor declined to name bidder whose plan was chosen, but it is known that the chosen bid was the lowest of the three, at $3.14 billon

    For more details on the three bids, see the public preview of the bridge designs



    September 19, 2012

    Governor Cuomo Announces Team to Help Select Final Bridge Design

    "Governor Andrew M. Cuomo today announced a selection review team for the new bridge to replace the Tappan Zee. The review team will include internationally renowned artists and architects, under the auspices of the New York State Council of the Arts, who will review proposed bridge designs as well as assist local community leaders and transportation experts in the evaluation process."

    Full press release



    September 18, 2012

    Grandview to Host a Community Meeting

    Thursday, September 20 at 7:00pm

    Grandview Village Hall
    118 River Road
    Grand View-on-Hudson, NY 10960

    For additional information, visit the project website at http://www.newnybridge.com



    August 9, 2012

    Nyack Chamber of Commerce and Nyack Center to Host a Community Meeting in Nyack

    Wednesday, August 15 at 6:00pm

    Nyack Center
    58 Depew Avenue
    Nyack, NY 10960

    For additional information, visit the project website at http://www.newnybridge.com



    August 3, 2012

    Tappan Zee Bridge Team to Host a Community Meeting in Nyack

    Monday, August 6 at 6:30pm

    Nyack Library
    59 South Broadway
    Nyack, NY 10960

    For additional information, visit the project website at http://www.newnybridge.com



    August 1, 2012

    Final Environmental Impact Statement Released

    The FEIS has been released and is available for public review until September 2, 2012

    Click here to view the FEIS

    Note: To view the FEIS, you will need Adobe Acrobat Reader. You can download it for free by clicking on the button below.

    For additional information, visit the project website at http://www.newnybridge.com



    July 27, 2012

    The Rockland County Community Meeting has been rescheduled for:

    Thursday, August 2nd, 2012 at 7:00pm

    Rockland Community College
    Technology Building
    145 College Road
    Suffern, NY

    Please RSVP at http://www.governor.ny.gov/webform/bridge-meeting




    June 14, 2012

    As part of the engineering tests for the new Tappan Zee Bridge, the State will set off a small explosion to test sub-bottom conditions. The blast will occur Friday, June 15 sometime between 10 am and 12 noon. They said the sound will be comparable to "a small firework going off. The detonation [will] create a vibration that will measure soil stability in the bed of the river."




    May 25, 2012

    The Department of Transportation announced today that the South Broadway overpass will not be replaced as originally planned. As a result, six properties in South Nyack that had been scheduled to be demolished for this purpose, will not be taken.

    For details, see the Village Press Release




    May 10, 2012

    Last Updated May 18, 2012

    As you probably literally heard, the Department of Transportation was driving piles into the riverbed on Saturday, May 5th. The noise was heard all over the Village. There was even a report of someone who was hiking on Hook Mountain and heard the noise. The pile driving continued until about 6:30 PM.

    Village officials contacted the Department of Transportation to lodge a complaint and to seek more information and also requested the DOT to give the Village advance notice of the schedule, so the residents can stay informed.

    The DOT has informed the Village that they are scheduled to drive another pile on the Westchester side on Saturday, May 12, in the afternoon.

    Two piles will be driven on the Rockland side on Wednesday, May 16, between 3:30pm and 6:00pm.

    The final pile will be driven mid-river on Friday, May 18. Vibrating will begin at about 10:00am. The piling will be hammered starting at about 1:00pm and last about 3 hours.

    This will complete the pile driving. After six or seven weeks, they may strike the piles a couple of more times to see if they have settled, but those strikes would be done in a few minutes.

    The pile driving is part of a pilot study to gather data for the Tappan Zee Bridge replacement project. They are driving test pilings into the riverbed to test how well they will support the weight of the new bridge. They are driving seven piles in total for the pilot project. Saturday saw the driving of the first two.

    Each pile takes about an hour and a half. They use a combination of vibrating and pile driving to set the piles. They are also testing sound mitigation techniques during the driving. They first measure without any mitigation and then try and measure different techniques. This is why the driving stops and then starts again. DOT has stated that they have noise measuring instrumentation in place at Salisbury Point and they also have a person walking around the village with a hand held device taking measurements.

    The DOT contract with the firm doing the work allows them to work from 7 AM to 7 PM seven days per week, but they don't generally work on Sundays. The Village has requested that the DOT instruct the contractor to abide by the Village's restrictions of 8 AM to 7 PM Monday through Friday, with quiet days on Saturday, Sunday, and holidays.

    The Trustees are deeply concerned about the disturbance this activity imposes on our community. We continue to push the state to minimize the impacts on our residents.

  • Overview

    The original Tappan Zee Bridge project had a devastating effect on South Nyack, cutting it in two. In 1952 New York State destroyed over 100 South Nyack homes and our entire business district in order to build the bridge.

    Now, 60 years later, the replacement of the Tappan Zee Bridge will once again impact no other community as much as South Nyack. There will be permanent changes and several years of construction that will affect our residents.

    Mayor DuBow, the Trustees and other Village officials are working diligently to fight to minimize negative impacts and to also try to bring some positive benefits to the Village. This letter to South Nyack residents is intended to give you details about how the project affects South Nyack and what the Village is doing to fight for South Nyack's interests.

    The Mayor and Trustees encourage you to keep informed, let your views be known, and become more involved where you can.

    Details about the new bridge landing in South Nyack

    The State has two alternative designs for the new bridge, but they are very similar with respect to how they affect South Nyack.

    The new bridge will come ashore in South Nyack just to the north of the current bridge and merge into the highway at about the same place as the current bridge landing.

    The limit of construction for the reconstructed highway in South Nyack is just west of the South Broadway overpass. In the current plan, no changes are proposed to Interchange 10. They do say, though, that Exit 10 could be used as a construction staging area.

    The new design has a pedestrian and bicycle path, the roadway that will be much higher than the existing roadway, and the South Broadway overpass will be replaced. Entire or portions of nine properties including six homes will be taken by eminent domain.

    The landing in South Nyack, new overpass design, and the propoerties to be taken can be viewed here:
    http://www.thenewtzb.com/deis/a2-short-span-option.pdf (See drawing B-4210, page 8)
    http://www.thenewtzb.com/deis/a3-long-span-option.pdf (See drawing B-4210, page 8)
    (The drawings are also available at Village Hall.)

    Shared-use path

    The new Tappan Zee Bridge is designed to have a pedestrian and bike lane (aka "shared-use path") on its north side. When it comes ashore in South Nyack, it runs along the north edge of the highway and ends at South Broadway. To accommodate the path, a slice of land is being taken from the Bradford Mews apartments and properties on Smith Avenue.

    Thruway will be taller

    The current highway is relatively flat as it heads east from South Broadway and onto the existing bridge. The causeway is flat and then rises steeply to the bridge's center span. The plans for the new bridge have the highway rising gradually and evenly from South Broadway to the center span. This means the highway will be quite a bit higher than the current highway from South Broadway to River Road. (The "long-span option" bridge is quite a bit taller than the "short-span option" bridge.)

    On the south side of the highway, the highway will be widened and a new retaining wall will be built. Along the south side, a 20' sound barrier is proposed. Several homes on Ferris and Bight Lanes will have their river views cut off completely.

    New South Broadway overpass

    In order to transition the highway traffic from the existing bridge onto the new bridge, as the new landing is built the traffic will be temporarily shifted north and south. In order to shift the traffic, they say they need to make the highway wider from South Broadway to the river. In order to widen the highway, they say they have to replace the South Broadway overpass. Their design for the new overpass has them taking six homes and a public pocket park by eminent domain.

    The current South Broadway overpass has a span of 148 feet and is held up in the middle by a pillar. (This is where the garage is for the truck that moves the TZB's movable barrier.) The new overpass' span across the highway is proposed to be 170 feet. Current Federal standards require the new overpass to have a clearance of 16.5 feet over the highway. Because of this, the new overpass will be taller than the current one and it's much more difficult to design the overpass to meet grade on either side.

    Also, because they will be shifting the traffic back and forth, they do not want a center pillar for the new overpass. Without a support below, the overpass is proposed to be supported from above with a truss, arch, or some other sort of superstructure. (This hasn't been designed, yet.)

    The new overpass is designed to be built and put into place next to the current overpass. This is so the current overpass can be kept open until the new one is ready. But it means the new design has more severe curves in it. It also means that two homes on the north side and one on the south side are taken. In addition, three more homes and the pocket park on the south side are taken to provide a construction staging area. The plan is to assemble the new overpass there and then lift it into place. Once the new overpass is in place the staging area would be freed up. While that land will be titled to the Thruway, they have hinted that they may be willing to eventually turn it over to the Village.

    Temporary Construction Impacts

    The project will take 4 to 5 years to build. During that time we can expect the greatest impact on South Nyack to be construction noise. Obviously, those closest to the highway will be most affected by this. The existing noise barrier along the north side will be taken down in order to widen the highway, so it will certainly be noisier until the new wall is in place.

    They will be driving large steel piles into the riverbed to support the new bridge. The pounding may be quite loud. They will be driving test pilings as soon as March, so we will soon get a taste of how loud this will be.

    There will be a lot of activity at the base of the bridge on the river shoreline. A large platform will be built out into the river for construction barges.

    Truck traffic is supposed to be contained to the Thruway itself, using the maintenance access ramps to River Road.

    Current plans for the replacement of the South Broadway overpass keep the existing overpass open to traffic until the new overpass is in place. There may be some temporary closures.

    Permanent Impacts

    The most significant permanent impacts of the new bridge to South Nyack are:

    Reduction in tax ratables

    The taking of properties will result in a reduction of tax revenue for the Village, Orangetown, school district, and fire district. This means that everyone else's taxes will go up to make up for the loss.

    Traffic Safety

    The new South Broadway overpass will have more severe curves in it, potentially making it more susceptible to accidents.

    Visual impacts

    The new TZB will be substantially taller through South Nyack. The "long-span" option is even taller than the "short-span" option. Several homes on Ferris and Bight Lanes will have their views of the river completely blocked.

    The new South Broadway overpass will be taller than the existing overpass. It will also have some sort of superstructure above the overpass. This will make it much more visually prominent.

    Parking

    The new shared-use path on the new bridge begins at the South Broadway overpass. (There is no direct connection to the Esposito Trail.) If the path becomes very popular, people may wish to park their cars in South Nyack, so they can then walk or bike on the path. The State has not conducted any studies predicting how many people will likely use the path and how many will likely drive to and park in South Nyack. There is no parking lot planned for near the path, so out-of-town path users drivers would have to park on local streets.

    Potential Benefits

    The State has claimed there are benefits to South Nyack from the new bridge:

  • The addition of shoulders on the new bridge will reduce traffic backups when there are accidents on the bridge.

  • The new shared-use bicycle/pedestrian path is a substantial new recreational benefit to South Nyack.

    The Trustees are skeptical about these claims, viewing them as minimal at best, especially when compared to the negative impacts the new project imposes on the Village.

  • What is the Village doing about the project?

    The Trustees and other Village officials have been fighting with the State to try to minimize the negative impacts of the project and also to try to bring some real, lasting benefits to South Nyack.

    As required by law, the project team recently published a Draft Environmental impact Statement (DEIS), detailing negative impacts of the project and their plans to mitigate those impacts. The Village has reviewed the DEIS and found many flaws and omissions. A written response detailing these defects has been sent to the project team and they are obligated to address our comments. The Village's DEIS response is posted here

    In response to pressure from the Village, the project team sent members to meet with Village officials to go over details about the project's effects on South Nyack. The team has agreed in principal to have additional meetings with the Village to allow us to try to come up with alternative designs for the South Broadway overpass that may work better for the Village.

    The Village has been looking for opportunities to leverage the bridge project to bring benefits to South Nyack. The State had until recently been proposing to redesign and reconstruct Exit 10. This would dramatically educe its footprint and free up land. This land could be used to help ease the tax burden on our residents. Village residents have expressed support of Mayor DuBow's proposal to build a "cap" or deck over the Thruway, reconnecting the two sides of the Village. The Village has proposed studying a potential local development project using the "cap" plus the freed-up Exit 10 land area.

    The Mayor and Village officials have been working with our elected State and Federal representatives to take a broader view of the Tappan Zee Bridge project. We are showing them how coordinating the project with our own proposal would be the most cost-effective way to reconnect our neighborhoods, bring lasting jobs, long-term economic sustainability, and an improved environment to the village we love and call home.

    What can you do to help?

    You can email or write to the State to let them know you support the Village's response to the DEIS. The deadline for comments is Friday, March 30, 2012. There is a template letter you can copy and email posted here

    Email comments to:

    tzbsite@dot.state.ny.us

    Mail written comments to:

    Michael P. Anderson
    Project Director
    New York State Dept. of Transportation
    4 Burnett Boulevard
    Poughkeepsie, New York 12603

    For more information or to become more involved, please contact:

    Mayor Tish DuBow
    845-358-0287
    mayor@southnyack.ny.gov


    Copyright © 2013 Village of South Nyack.  All Rights Reserved.